CEDAR RAPIDS, Iowa (AP) - The city of Cedar Rapids is preparing to undertake more than $7.4 million in construction work next year on its flood control system.

The city will open bids this month for key projects, including demolition of a bridge and construction of a permanent levee and gatewell in Czech Village, the Gazette reported. Bids will also open for construction of a flood wall, pump stations and watermain protecting the Quaker Oats plant along the riverfront.

Work on the Czech Village project is estimated at $2.1 million and is expected to begin in the spring and be complete next fall. Work on the Shaver Road NE Bridge demolition is estimated at $2.5 million and will accommodate a new bridge and adjacent flood walls along with flood protection. That work is expected to begin in November.

People were interested in these podcasts

The Quaker Oats plant project is underway, but the third phase - which includes the flood wall, pump stations and watermain, is expected to be completed next year. Once done, the fourth phase to build a 42-foot-wide, 11-foot-high miter gate flood closure at the Union Pacific Railroad will start in May for an estimated $2 million.

Cedar Rapids, the state’s second-largest city, was devastated by historic flooding in 2008 flood that wiped out downtown neighborhoods.