By Associated Press - Tuesday, March 7, 2017

SEATTLE (AP) - The Seattle tunnel boring machine known as Bertha is back on a slightly shifted course after additional measurements confirmed it was 6 inches east of the correct site.

The Seattle Times reports (https://goo.gl/LC7l1N ) the drill resumed digging Monday following a stoppage that included three rounds of surveys.

Operators will gradually steer Bertha back on course.

People were interested in these podcasts

Seattle Tunnel Partners used the stoppage to replace some of the 600-pound disc-shaped cutter blades.

State transportation officials say tunnel contractors are considering whether to perform additional measurements.

The $2.1 billion downtown-bypass tunnel from Sodo to South Lake Union is expected to open to traffic in early 2019, followed by demolition of the Alaskan Way Viaduct.

___

Information from: The Seattle Times, https://www.seattletimes.com