By Associated Press - Friday, December 23, 2016

BILLINGS, Mont. (AP) - A wind farm west of Billings has a new 25-year contract to sell power to NorthWestern Energy.

The Billings Gazette reports (https://bit.ly/2i0I078 ) that Billings-based WKN Montana will break ground in late spring on the Vivaldi Springtime Wind Project in the hills north of Reed Point.

The 25-to-35-turbine project is expected to be finished in early 2018. It will produce about 80 megawatts of energy, enough to power 19,000 to 30,000 homes.

People were interested in these podcasts

WKN will receive $37.65 a megawatt hour for its energy.

Under 40-year-old federal laws to promote renewable energy, the Vivaldi project is classified as a “qualifying facility” and Northwestern cannot say no to the power and must offer a long-term contract. Projects are, however, subject to a negotiated price.

___

Information from: The Billings Gazette, https://www.billingsgazette.com